As a project team grows, complexity grows exponentially. Use this formula to determine the number of potential communication paths between stakeholders.

The Formula

$$ \text{Channels} = \frac{N(N-1)}{2} $$

Where N = Total Number of Stakeholders

Key Concepts

  • Exponential Growth: A small increase in team size leads to a massive jump in complexity.
  • Who is 'N'? 'N' represents everyone who communicates, including the Project Manager, team, and sponsors.

PMP® Exam Tip

If a question says "10 team members and a project manager," don't use 10!
N = 11 (10 members + 1 PM).

Quick Calculator

*Remember to include yourself (the PM).

Communication Paths