Project Scope Baseline: WBS
Heart of Harmony Community Center: Defining the ‘WHAT’ of the Project
The WBS is the hierarchical decomposition of the total scope of work to be carried out. It ensures **100% of the project scope** is captured down to the **Work Package** level, which is necessary for accurate estimation and control.
1.0 Heart of Harmony Community Center Project
1.1 Project Management
- 1.1.1 Project Planning & Initiation
- 1.1.2 Project Execution & Monitoring
- 1.1.3 Project Control & Reporting
- 1.1.4 Project Closeout
- 1.1.5 Stakeholder Management & Communication
1.2 Design & Permitting
- 1.2.1 Feasibility Studies & Site Analysis
- 1.2.2 Conceptual Design
- 1.2.3 Schematic Design
-
1.2.4 Detailed Architectural & Engineering Design
- 1.2.4.1 Structural Design
- 1.2.4.2 Electrical Design
- 1.2.4.3 Plumbing Design
- 1.2.4.4 HVAC Design
- 1.2.4.5 Civil Engineering Design
- 1.2.4.6 Landscape Design
-
1.2.5 Regulatory Approvals & Permitting
- 1.2.5.1 Municipal Building Permits
- 1.2.5.2 Environmental Permits
- 1.2.5.3 Accessibility Certifications
- 1.2.5.4 Sustainability Certifications (LEED)
- 1.2.6 Tender Document Preparation
1.3 Procurement & Contracts
- 1.3.1 Contractor Selection
- 1.3.2 Material & Equipment Procurement
- 1.3.3 Contract Management
1.4 Site Prep & Foundation
- 1.4.1 Site Survey & Geotechnical
- 1.4.2 Site Clearing
- 1.4.3 Earthworks & Grading
- 1.4.4 Foundation Construction
1.5 Building Construction
- 1.5.1 Structural Framing
- 1.5.2 Roof Installation
- 1.5.3 Exterior Walls & Cladding
1.11 Project Closeout
- 1.11.1 Financial Closeout
- 1.11.2 Lessons Learned & Final Report
- 1.11.3 Grand Opening Execution