The PMP Formula Master Sheet

 

 

 

Quick Reference

PMP® Formula Cheat Sheet

The essential 2026 formulas for Cost, Schedule, and Communications.

Earned Value Management

CV (Cost Variance) EV – AC

Negative is Over Budget | Positive is Under Budget

SV (Schedule Variance) EV – PV

Negative is Behind Schedule | Positive is Ahead

CPI (Cost Index) EV / AC

Efficiency: > 1.0 is Good | < 1.0 is Bad

Estimating & Channels

PERT (Beta) (O + 4M + P) / 6

Weighted average for activity duration

Comms Channels N(N-1) / 2

Calculates complexity between N stakeholders

Standard Deviation (P – O) / 6

Measures the level of risk/uncertainty